Custom Home Change Orders: Keep Upgrades Clear Before the Work Moves On
The best time to resolve scope, price and schedule effect is before the changed work is installed. A clean process protects the homeowner experience and the builder's project record.
Separate selection from change
Choosing an item within the contract or allowance may not be a change. Added scope, upgraded cost or changed work should be identified explicitly.
Price the complete effect
Include direct trade or material cost plus the contractually appropriate markup and any related work. State exclusions instead of leaving them assumed.
Get approval at the right time
Emergency conditions exist, but routine upgrades should not rely on verbal memory after installation.
Update budget and billing
Once approved, carry the change into the current contract, project budget, affected commitment and billing process.
Project review checklist
• Is the request actually outside the current contract scope? • Does pricing include related work and stated exclusions? • Is approval documented before routine changed work proceeds? • Does the approved change update downstream records?