Construction Change Order Cost Impact Calculator
Price a proposed change from known direct costs and a markup percentage, then show the revised contract value if the owner approves the change.
Price a proposed change from known direct costs and a markup percentage, then show the revised contract value if the owner approves the change.
Proposed change price = direct cost × (1 + markup percentage). Revised contract if approved = existing approved contract + proposed change price. Markup on cost and profit margin are not the same.
A $6,000 direct-cost change marked up 20% becomes a $7,200 proposed change. Against a $125,000 contract, approval would result in $132,200.
Use scope-specific labor, material, subcontract, fees, taxes and general conditions. Do not treat an unapproved proposal as revenue.
These results are for project planning, not contractual certification, approved quantities or construction payment authorization.
Read the related construction management guide to understand the records and approvals underlying these calculations.