How to calculate it
Retainage withheld = approved completed work × retainage rate. Net earned = completed work − retainage. Estimated current amount due = max(0, net earned − prior payments). Remaining contract = max(0, contract − completed work).
Worked example
For $40,000 in approved work and 10% retainage, $4,000 is withheld. Before other deductions, $36,000 is net earned. If $10,000 was previously paid, the arithmetic balance is $26,000.
What should you check before using the result?
Review stored materials, prior billings, retainage release, contract terms, state payment rules, credits and approvals.
These results are for project planning, not contractual certification, approved quantities or construction payment authorization.
Related guidance
Read the related construction management guide to understand the records and approvals underlying these calculations.
Use this in your projects
VegaUltimate manages project records, scheduling, financial controls and communication. This standalone calculator is free and does not store your inputs.
Create a VegaUltimate workspace · Use the calculator inside VegaUltimate