VegaUltimate · Home · Free calculators · Pricing

Construction Schedule Delay Cost Calculator

Estimate extended project general conditions from additional schedule days and daily site operating expenses. This is a planning worksheet, not a finding of delay responsibility.

Enter your project numbers

How to calculate it

Daily extension cost = daily supervision + temporary facilities/rentals + other site overhead. Extension estimate = delay days × daily extension cost.

Worked example

Twelve extra days at $350 supervision, $125 temporary equipment and $180 other daily conditions equal $655 per day and $7,860 in potential extended cost.

What should you check before using the result?

Separate excusable, compensable, concurrent and contractor-caused delay. Check notice requirements, baseline schedule and documentation.

These results are for project planning, not contractual certification, approved quantities or construction payment authorization.

Related guidance

Read the related construction management guide to understand the records and approvals underlying these calculations.

Use this in your projects

VegaUltimate manages project records, scheduling, financial controls and communication. This standalone calculator is free and does not store your inputs.

Create a VegaUltimate workspace · Use the calculator inside VegaUltimate