Construction Job Cost Variance Calculator
Compare an approved construction budget with actual spending and the estimated cost to complete. The output is a forecast, not just a backward-looking actual-cost report.
Compare an approved construction budget with actual spending and the estimated cost to complete. The output is a forecast, not just a backward-looking actual-cost report.
Forecast final cost = actual cost to date + cost still expected to finish. Forecast variance = approved budget − forecast final cost. Commitments are displayed for context, not added automatically, since invoice amounts may already be included in actual costs.
A $125,000 budget with $35,000 spent and $70,000 to finish forecasts $105,000 total cost, leaving a $20,000 favorable variance if assumptions hold.
Validate unfinished subcontract commitments, change orders, contingency and whether cost-to-complete already includes committed work.
These results are for project planning, not contractual certification, approved quantities or construction payment authorization.
Read the related construction management guide to understand the records and approvals underlying these calculations.