Construction Job Cost Variance Calculator

Compare an approved construction budget with actual spending and the estimated cost to complete. The output is a forecast, not just a backward-looking actual-cost report.

Enter your project numbers

How to calculate it

Forecast final cost = actual cost to date + cost still expected to finish. Forecast variance = approved budget − forecast final cost. Commitments are displayed for context, not added automatically, since invoice amounts may already be included in actual costs.

Worked example

A $125,000 budget with $35,000 spent and $70,000 to finish forecasts $105,000 total cost, leaving a $20,000 favorable variance if assumptions hold.

What should you check before using the result?

Validate unfinished subcontract commitments, change orders, contingency and whether cost-to-complete already includes committed work.

These results are for project planning, not contractual certification, approved quantities or construction payment authorization.

Related guidance

Read the related construction management guide to understand the records and approvals underlying these calculations.

Use this in your projects

VegaUltimate manages project records, scheduling, financial controls and communication. This standalone calculator is free and does not store your inputs.

Create a VegaUltimate workspace · Use the calculator inside VegaUltimate