Construction Job Cost Variance Calculator
Compare approved budget, committed cost, actual cost and estimated cost to complete.
Enter project figures
Calculated amounts
- Approved job budget
- $125,000.00
- Committed cost (reference; not double-counted)
- $90,000.00
- Actual cost to date
- $35,000.00
- Forecast final cost
- $105,000.00
- Forecast budget variance (positive = under budget)
- $20,000.00
Commitments and actual costs can overlap. Do not add the full committed total to actual costs unless the remaining commitment excludes paid work.