Construction Schedule of Values Calculator
Estimate a progress-billing line from its approved scheduled value and current completion percentage. Keep prior billing and retainage separate to avoid overstating the current application.
Estimate a progress-billing line from its approved scheduled value and current completion percentage. Keep prior billing and retainage separate to avoid overstating the current application.
Earned value = scheduled value × completed percentage. Retainage = earned value × retainage rate. Net earned = earned − retainage. Current due estimate = max(0, net earned − previous billing).
For a $125,000 line at 35% complete, earned work is $43,750. Ten percent retainage reduces net earned to $39,375 before accounting for previous billings.
Stored materials, disputed progress, approved change orders, prior periods and payment authorization must be reconciled.
These results are for project planning, not contractual certification, approved quantities or construction payment authorization.
Read the related construction management guide to understand the records and approvals underlying these calculations.