Construction Schedule of Values Calculator

Estimate a progress-billing line from its approved scheduled value and current completion percentage. Keep prior billing and retainage separate to avoid overstating the current application.

Enter your project numbers

How to calculate it

Earned value = scheduled value × completed percentage. Retainage = earned value × retainage rate. Net earned = earned − retainage. Current due estimate = max(0, net earned − previous billing).

Worked example

For a $125,000 line at 35% complete, earned work is $43,750. Ten percent retainage reduces net earned to $39,375 before accounting for previous billings.

What should you check before using the result?

Stored materials, disputed progress, approved change orders, prior periods and payment authorization must be reconciled.

These results are for project planning, not contractual certification, approved quantities or construction payment authorization.

Related guidance

Read the related construction management guide to understand the records and approvals underlying these calculations.

Use this in your projects

VegaUltimate manages project records, scheduling, financial controls and communication. This standalone calculator is free and does not store your inputs.

Create a VegaUltimate workspace · Use the calculator inside VegaUltimate