Construction Schedule of Values Calculator
Calculate billing-period earned value and current payment from scheduled value and completion percentage.
Enter project figures
Calculated amounts
- Scheduled value
- $125,000.00
- Earned value to date
- $43,750.00
- Retainage to date
- $4,375.00
- Net earned
- $39,375.00
- Current amount due after prior billed
- $24,375.00
Use approved contract SOV lines and independently confirm prior billed amounts, stored materials, withholding and contract terms.