Baseline and approved revisions
Set the accepted estimate as the original budget by cost code, then keep approved changes beside it so movement over time is explainable.
Committed versus actual cost
Record subcontract and purchase-order commitments separately from invoices paid, or the same dollars get counted twice in the cost report.
Approved change orders
Post each approved change to the budget line it affects before the work is treated as authorized.
Forecast to complete and margin
Add actual cost to remaining cost to complete to see forecast final cost and projected margin, not just spend to date.